An excerpt from an independent estimate and findings report, in the format a client receives. This is a format sample: the project is illustrative, not a client job.

Download Excel Download PDF

Riverside Community Library (illustrative) · Three-story renovation and addition, 54,000 SF · 90% CD estimate · Rev 2

Estimate (excerpt)$1.74M – $2.12M
Lines, full deliverable312
Findings7
RFIs drafted3
Estimate_Rev2.xlsx · Envelope & MEP excerptDrawn by Ladder AI · Reviewed by cost professional ✓
RefDescriptionQtyUnitRate basisTotal (range)Conf.Source
07 54 23TPO roofing, 60 mil, fully adheredIncl. tapered insulation & flashings18,400SFUnit rate, regional bids$410k – $470kSpec §2.2
A-501, A-502
08 71 00Door hardware setsPer hardware schedule, 9 set types146EASet rate by type$118k – $139k08 71 00
A-601 schedule
08 44 13Curtain wall, thermally brokenRFI #7Head height not dimensioned6,900SFRange until height confirmed$0.96M – $1.22MA-301
Spec 08 44 13
23 74 13Packaged rooftop units, 25 tonAddendum 3RTU-3 resized4EASupplier quotes (2)$212k – $236kM-401 schedule
Add. 3 item 12
02 41 19Selective demolition, interior partitionsAllowancePending existing-conditions survey25,600SFAllowance$38k – $57kD-101
Note 4
Excerpt subtotal $1.74M – $2.12MIn this excerpt: 1 RFI open · 1 addendum change · 1 allowance

Findings report

What the documents don’t tell you.

Every estimate ships with this list, written as questions your design team can answer before bids open.

Gaps · missing information

  1. Curtain wall head height at level 3 not dimensioned.A-301
  2. No existing-conditions survey for interior demolition.D-101
  3. Roof drain count missing from plumbing plans.P-201

Conflicts · documents disagree

  1. Spec calls for phenolic toilet partitions; finish schedule says HDPE.10 21 13 · A-801
  2. Hardware set 4 lists closers the door schedule omits.08 71 00 · A-601

Assumptions & allowances

  1. Demolition carried as an allowance until the survey arrives.02 41 19
  2. RTU-3 priced at the Addendum 3 size, not the original schedule.Add. 3

RFIs, ready to send

Numbered to continue the project’s RFI log (#1–#6 already issued).

  1. RFI #7: confirm curtain wall head height.A-301
  2. RFI #8: confirm toilet partition material.10 21 13
  3. RFI #9: confirm closers on hardware set 4.08 71 00